Gorkha. A survey of hydropower generation has been started in eight different places in the district. The Department of Electricity Development has given survey permission to eight companies to generate electricity from six rivers and streams.
Two companies have received permission for the survey of electricity generation in Budhigandaki. Chilime Hydropower Company has been given survey permission to construct the 93-megawatt capacity ‘Budhigandaki Proc-1 Hydropower Project’ in Proc. Both companies are engaged in the survey to complete the survey within the current fiscal year.
Nabil Developers has received permission to construct the 203-megawatt capacity ‘Upper Budhigandaki Hydropower Project’ in Chunchet and Sirdibas. Pelma Hydropower Project has been granted a survey permit to generate 90 megawatts of hydropower from Marsyangdi. The company has stated that it will complete the survey work for the construction of the ‘Marsyangdi Khola Hydropower Project’ in Palungtar Municipality of Gorkha and Bhanu Municipality of Tanahun by the coming Asoj.
MA Energy Ventures has also received a permit to conduct a hydropower survey in Gorkha. The company is going to conduct a survey for the construction of the 14.9 MW capacity ‘Daraudi/Marsyangdi Hydropower Project’ from Deurali, Manakamana and Daraudi in Bakrang in Shahid Lakhan Rural Municipality.
Khandah Hydropower Pvt. Ltd. has started conducting a survey for the construction of the ‘Super Daraudi Khola E Hydropower Project’. The company has stated that the survey of the proposed 9.4 MW capacity project to be built in Barpak will be conducted by 2083 Shrawan.
Gorkha Daraudi Hydropower Pvt. Ltd. has obtained a license for the construction of a 7 MW capacity hydropower project in Dordi Khola in Barpak. The company is conducting a survey for the construction of the ‘Super Daraundi-Paukhola Hydropower Project’ by Asoj 2083. Meta Urja Pvt. Ltd. has stated that it is conducting a survey for the construction of the 5.2 MW ‘Upper Dobhan Khola Hydropower Project’ in Dobhan Khola of Dharche Rural Municipality-1 with a view to completing the work by Pus 2083.
Similarly, Pelton Hydro Energy Pvt. Ltd. has obtained survey permission for the construction of the 13 MW ‘Upper Yaru Khola Hydropower Project’ from Yaru Khola in Keraunja. The company has stated that it has started the survey work with a view to completing it by Pus 2083.